Home > Search > Docket Search > Docket Details

Docket Details




E-00000D-02-0065

Various Electric Companies (A.C.C.)


Electric

Generic

Closed

1/24/2002

Biennial Electric Transmission Assessment for Ten Year Period 2002 - 2011 for electric transmission lines

02-0065

 
Filing Date
Description Filed By Filed For Document Details PDF
1/29/2003 Decision - Directing the Administrative Closure of the Docket Colleen A. Ryan, Docket Administrator (#65562)
1/23/2003 Staff's Directive for Administrative Closure Ernest G. Johnson, Director Utilities Division, A.C.C.
12/24/2002 Notice of Filing - Miscellaneous P. Plus Corporation (Second Biennial Transmission Assessment 2002-2011)
12/19/2002 Decision A.C.C. (#65476)
12/13/2002 Miscellaneous Comments Raymond S. Heyman, Atty. (TEP's Comments to The 2nd Biennial Transmission Assessment 2002-2011)
12/13/2002 Motion/Request - Miscellaneous Kelly J. Barr, Atty. - SRP
12/6/2002 Proposed Order from the Utilities Division Utilities Division
10/10/2002 Miscellaneous Changes Jay L. Shapiro, Atty.
10/4/2002 Miscellaneous Comments Resal A. Craven (Citizens Communications' Comments on the 2nd Biennial Transmission Study Draft Report)
10/4/2002 Miscellaneous Comments Paul R. Michaud, Atty. (By filing Comments on Welton-Mohawk Generating Facility's Second Biennial Transmission Assessment Draft Report)
10/4/2002 Miscellaneous Comments Roger K. Ferland, Atty. (By filing Harquahala's Comments on Second Biennial Transmission Assessment Staff's Draft Report)
10/4/2002 Miscellaneous Comments Jana Van Ness, Manager - State Regulation, APS (Comments on Draft Biennial Transmission Assessment)
3/27/2002 Compliance - Ten Year Plans D.L. True - Superintendent (10-year plan for Morenci Water & Electric Company)
2/20/2002 Compliance - Ten Year Plans Stan Marks - Vice President (10-year plan for NRG MexTrans. Inc (a subsidiary of NRG Energy, Inc.)
2/15/2002 Compliance - Ten Year Plans Marjorie J. Haberman - Paralegal (10-year plan for the Public Service Company of New Mexico - originally sent on 1/31/02)
2/6/2002 Compliance - Ten Year Plans Raymond S. Heyman - Atty. (Amendment to TEP's 10-year plan)
2/4/2002 Compliance - Ten Year Plans No signature on document (10-year plan for Southwest Transmission Cooperative, Inc. Section II contains the Winchester Interconnect Project Report)
2/1/2002 Compliance - Ten Year Plans Ed Beck - Supervisor (10-year plan for Tucson Electric Power Co.)
1/31/2002 Compliance - Ten Year Plans Jeffrey B. Guildner - Atty. (10-year plan for Reliant Energy Signal Peak)
1/31/2002 Compliance - Ten Year Plans Dennis Malone (10-year plan for El Paso Electric)
1/31/2002 Compliance - Ten Year Plans Douglas V. Fant (10-year plan for Power Up Corporation)
1/31/2002 Compliance - Ten Year Plans Paul R. Michaud - Atty. (10-year plan for Wellton-Mohawk Generating Facility)
1/31/2002 Compliance - Ten Year Plans C. Webb Crockett - Atty. (10-year plan for Panda Gila River)
1/31/2002 Compliance - Ten Year Plans Hugh Holub (10-year plan for Ambos Nogales Generating Station and Maestros Group)
1/31/2002 Compliance - Ten Year Plans Gary Ijams (10-year plan for Central Arizona Water Conservation District [CAP])
1/31/2002 Compliance - Ten Year Plans Jana Van Ness - Manager, State Regulation (10-year plan for APS)
1/31/2002 Compliance - Ten Year Plans Kelly J. Barr - Manager (10-year plan for SRP)
1/30/2002 Compliance - Ten Year Plans Hugh Holub (10-year plan for Ambos Nogales Generating Station & Maestros Group)
1/30/2002 Compliance - Ten Year Plans Thomas J. Ferry (10-year plan for Citizens Communications Co.)
1/30/2002 Compliance - Ten Year Plans Lawrence V. Robertson, Jr. - Atty. (10-year plan for Toltec [Docket #'s 01-0112 & 01-0113)
1/30/2002 Compliance - Ten Year Plans Lawrence V. Robertson, Jr. - Atty. (10-year plan for Bowie Power Station [Docket #'s 01-0118)
1/30/2002 Compliance - Ten Year Plans Michael M. Grant - Atty. (10-year plan for Alleghney Energy Supply)
1/29/2002 Compliance - Ten Year Plans Robert E. Castillo - VP, New Mexico Operations
1/28/2002 Compliance - Ten Year Plans Thomas H. Campbell - Atty.
1/24/2002 Compliance - Ten Year Plans Thomas H. Campbell - Atty. (10-year plan for Duke Energy Arlington Valley)
1/24/2002 Application - Opened by Memorandum Ernest G. Johnson, Director - Utilities Division, A.C.C.
Decision # Decision Date Description PDF
65476 12/19/2002 Decision
65562 1/29/2003 Decision - Directing the Administrative Closure of the Docket
 
Location Type Date Time Completed Details Download Outlook Calendar
N/A Open Meeting 12/17/2002 9:00 AM 12/17/2002
Case Staff
Name Area Assigned
Gellman Legal Division 2/12/2002
8/6/2005
8/6/2005

No service listings for this docket were found.

There were no linked dockets found